Log Entries For Rear Fuselage
| Date | Summary |
|
May 14, 2013
|
Bits and Pieces
|
|
May 11, 2013
|
Secured Pitot, Static and AOA Lines
|
|
Aug 24, 2012
|
Bulkhead #1 Reinstalled
|
|
Aug 2, 2012
|
Tailcone Riveting Completed
|
|
Jul 31, 2012
|
More Fiddlin'
|
|
Jul 22, 2012
|
Fiddlin
|
|
Jul 17, 2012
|
Empennage removed
|
|
Jul 12, 2012
|
Stinger Is Finished
|
|
Jul 11, 2012
|
Adjusted Stabilator
|
|
Jul 7, 2012
|
Stinger Almost Completed
|
|
Jul 5, 2012
|
More Stinger Work
|
|
Jul 4, 2012
|
Continued Stinger Fitting
|
|
Jul 1, 2012
|
Stinger Fitting
|
|
Jun 30, 2012
|
Lower Stinger
|
|
Jun 28, 2012
|
Upper Stinger
|
|
Jun 25, 2012
|
Completed Vertical Stab Trimming
|
|
Jun 24, 2012
|
Vertical Stab Trimming
|
|
Jun 19, 2012
|
Bulkhead #2 Riveting and Minor Skin Rework
|
|
Jun 17, 2012
|
More Static System and ADAHRS Mount Progress
|
|
Jun 15, 2012
|
More Tailcone Detail Work
|
|
Jun 14, 2012
|
Started Static Line Installation
|
|
Jun 13, 2012
|
Trim Motor Installed
|
|
Jun 10, 2012
|
Stab Trim Motor Installation Details
|
|
Jun 5, 2012
|
Pitch Servo Installation Details
|
|
Jun 3, 2012
|
Installed Auto pilot Pitch Servo
|
|
May 30, 2012
|
Back to Work...
|
|
May 3, 2012
|
Fuselage Joined For the First Time
|
|
Apr 30, 2012
|
ELT Trial Mounting
|
|
Apr 29, 2012
|
Replacement Tailcone Skin Completed
|
|
Apr 25, 2012
|
Back at it!!
|
|
Apr 14, 2012
|
Vertical Stab Mounted
|
|
Apr 9, 2012
|
Bellcrank Mocked Up
|
|
Apr 8, 2012
|
Tailcone Closeout Installed
|
|
Apr 7, 2012
|
Static Ports Installed and Stab Trim Harness Run
|
|
Apr 6, 2012
|
Completed LowerTailcone Riveting
|
|
Apr 4, 2012
|
Left Lower Tailcone Skin Riveted
|
|
Apr 3, 2012
|
Continued Tailcone Build up
|
|
Apr 2, 2012
|
Trim Actuator Shaft Installed
|
|
Mar 27, 2012
|
Continued Tailcone Assembly
|
|
Mar 22, 2012
|
Tailcone Riveting Started
|
|
Mar 20, 2012
|
Continued Tailcone Buildup
|
|
Mar 19, 2012
|
A Bit of Repair
|
|
Mar 17, 2012
|
Tailcone Build Up Continues
|
|
Mar 15, 2012
|
Started Tailcone Final Assembly
|
|
Mar 13, 2012
|
Tailcone Preps Complete
|
|
Mar 12, 2012
|
Completed Tailcone Stringer and Stiffener Preps
|
|
Feb 26, 2012
|
No Work....No Daytona 500
|
|
Feb 24, 2012
|
Continued Preps
|
|
Feb 19, 2012
|
Completed Disassembly
|
|
Feb 18, 2012
|
More Tailcone Prep
|
|
Feb 17, 2012
|
Tailcone Disassembly Continues....
|
|
Feb 16, 2012
|
Continued Tailcone Disassembly
|
|
Feb 15, 2012
|
Time to Disassemble
|
|
Feb 13, 2012
|
Fabricated ADAHRS Mount
|
|
Feb 12, 2012
|
Wrestling the Top Skin
|
|
Feb 10, 2012
|
More Tailcone Progress
|
|
Feb 8, 2012
|
Vertical Stabilizer Mated to Tailcone
|
|
Feb 7, 2012
|
Tailcone Closeout Skin
|
|
Feb 5, 2012
|
Longerons Drilled #40
|
|
Feb 4, 2012
|
Details, Details....
|
|
Jan 29, 2012
|
Tailcone Work Continues
|
|
Jan 28, 2012
|
Minor Tailcone Work Continues
|
|
Jan 26, 2012
|
Alternate Trim Servo Mounting Complete
|
|
Jan 25, 2012
|
More Tailcone Work
|
|
Jan 24, 2012
|
Oops Corrected...Time to Build On!!
|
|
Jan 23, 2012
|
Bulkhead #5 Build Up Oops....
|
|
Jan 20, 2012
|
Bulkhead #5 Prep Continues
|
|
Jan 18, 2012
|
Continued Bulkhead #5 Prep Work
|
|
Jan 17, 2012
|
Bulkhead #5 Initial Mock-up
|
|
Jan 16, 2012
|
Bulkhead Blues....
|
|
Jan 15, 2012
|
First Fit Up of Tailcone
|
|
Jan 10, 2012
|
Miscellaneous Tailcone Tasks
|
|
Jan 8, 2012
|
Tailcone Started
|
|