Oct 18, 2011 Solid Riveted Heavier Doubler to Spar
Oct 16, 2011 Fitted Spar Doubler
Nov 6, 2010 Solid Riveting 1440# Spar Doubler
Feb 6, 2010 Assembled Right Wing Skeletons #7, 8 & 9
Feb 3, 2010 Assembled Left Wing Skeletons 5 and 6
Feb 1, 2010 Assembled Left Wing Skeleton #3 and started #4
Jan 4, 2010 Rivet on Spar Extensions
Dec 16, 2009 Spars 10 and 11
Dec 12, 2009 Worked on Spars 8 & 9
Dec 11, 2009 GTB Finished Riveting Left Spar #1
Dec 9, 2009 Finished Spar #5
Dec 7, 2009 Assembling Spar #5
Dec 5, 2009 Riveted Spar #4
Dec 2, 2009 Riveted Spar 3 & Laid Out Spar #4
Nov 30, 2009 Assembled 3rd Spar
Nov 29, 2009 Finished Riveting the 2nd Spar
Nov 28, 2009 Assembled Second Spar
Nov 25, 2009 Preparing other Spar Blanks
Nov 23, 2009 Finished Riveting First Spar
Nov 21, 2009 Riveted First Spar
Nov 18, 2009 Drilling First Spar
Nov 16, 2009 Laying out Spar Web onto Spar
Nov 14, 2009 Cut Spar Webs
Nov 11, 2009 Cut Spar Angle Webs
Nov 9, 2009 Finished Cutting Spars
Nov 4, 2009 Spar Cutting
Nov 2, 2009 Started Cutting Spars